January 2022
Construction has begun on the Moggill Rd roundabout upgrade at Indooroopilly. Works will take place 7am to 6pm, Monday to Saturday. Additional night works will take place from 7:30pm to 5:30am, Sunday to Thursday. The following roads will be impacted:

Moggill Rd:

  • Night works lane closures

Moggill Rd Service Road (commercial):

  • Night works restricted access
  • Changes to parking hours

Coonan St:

  • Reduced to single lane northbound approaching the roundabout

Keating St:

  • Permanent removal of right hand turns into and out of Keating St
  • Left hand turn into Keating St maintained with changed traffic conditions

Nelson Pde:

  • Permanent closure of Nelson Pde at Moggill Rd
  • Minor vegetation removal

Waverley Rd:

  • Night works lane closures

Payne St:

  • Temporary closure of Payne St at Moggill Rd

Manchester Rd and Vincent St:

  • Day works lane closures

Stamford Rd, Station Rd and Stanley St near Moggill Rd intersections:

  • Day works lane closures
  • Night works lane closures

Underhill Ave:

  • Temporary reduction of on-street parking
  • Restricted access at northern end of Underhill Ave
  • Minor vegetation removal


August 2021

Building removal works to facilitate the Indooroopilly roundabout upgrade have commenced. Works will take place from 7am to 6pm, Monday to Friday and are due for completion by the end of September. These works will involve temporary lane closures on Moggilll Rd and Coonan St as required.

Main construction works will commence later this year, and will take place at night. The project is due for completion in 2024.


June 2021

Council have released the final plans for the $120m Indooroopilly Roundabout Upgrade project with preliminary works due to commence in the coming weeks (see below). The upgrade will include the construction of a t-intersection overpass from Coonan St over Moggill Rd, and Council will maintain the existing left-turn movement from Stamford Rd and allow westbound traffic a left-turn into Stamford Rd from Moggill Rd.

Early works will involve temporary lane closures on Moggilll Rd and Coonan St as required. Main construction works will commence in late 2021, and will take place at night. The project is due for completion in 2024.

I’m still not sure this is the best design as the t-intersection overpass will stop traffic using the Coonan Rd corridor in two locations whne completed rather than the current one at the round-a-bout.

 


December 2019

Brisbane City Council has finally provided answers to my questions about the Moggill Rd Round-a-bout upgrade. I also met with Council’s project team to discuss the draft designs and came away with even more questions.

This is a complex project with a large number of incidental impacts for local traffic movements. You can read the answers below. Most of them are fairly generic answers. Here are some highlights (all times are estimates):

  • Option A (T-intersection) – AM peak travel time –  25s slower; PM peak travel time – 12s faster;
  • option B (Overpass) – AM peak travel time 8s faster; PM peak travel time – 16s faster;
  • traffic signal phasing has not been determined;
  • the length of the slip lane in Option B and merge control is not determined yet;
  • access to the Indooroopilly strip shops will be via the McDonalds intersection  (Allwood St) and Clarence Rd, as Keating St becomes left in-left out only;
  • no cycling facilities;
  • no decision on the future use of remnant land around the round-about site; and
  • the project does not upgrade Coonan St south of the McDonalds intersection (Allwood St).

Neither Option A nor Option B have enough information yet to make an informed decision. However, Option A will make things worse for traffic using Coonan St in the AM peak by approximately 25s. Council is seeking feedback in the next few weeks. I have been advised the plan is then to choose one option and prepare a business case, with the preferred option to be released for further consultation in early 2020. It is really hard to see how this will benefit residents in the south-western suburbs other than an expected reduction in accident severity. In my view an overpass is needed, but the current draft design raises more questions than answers with so many design variables and technical issues not determined.

It is critical that you speak up now, as Council will make a decision that could adversely impact on our community for decades. Email your feedback to cityprojects@brisbane.qld.gov.au or call the project team on 1800 010 705.

Moggill Rd Roundabout Questions and Answers